Project List for 2020 Reopening

NYS Canal Corporation – Project List for 2020 Reopening                                                                                                                         updated 05.19.20

 

NY Forward Region and Forecasted Opening

Project

Scope of Work

Estimated Completion Date*

Western New York

Locks open by July 4th

Lock E-34/35

Lock maintenance

Complete

Lockport dry dock

Dry dock gate repair

Complete

 

 

 

Finger Lakes

Locks open by July 4th except Lock E-26

and Lock CS-2/3

Lock E-26

Lock maintenance

July 13

Lock E-33

Lock maintenance

Complete

Lock CS-2/3

Lock rehabilitation

August 3

Lock CS-4

Sinkhole repair

July 4

 

 

 

Central New York

Locks open by July 4th except Lock O-7

Lock O-7

Lock rehabilitation

August 10

Lock E-23

Lock maintenance

July 4

 

 

 

Mohawk Valley

Locks opening in phases between July 4th and

August 10th

Lock E-19

Lock maintenance

August 10

Embankment repair at E-19

Embankment repair

July 20

Lock E-13

Lock maintenance

July 27

Realls Creek dredging

Dredging

May 25

 

 

 

Capital District

Locks open by July 4th except Locks E-7, E-8,

E-9 and Lock C-12

Lock C-12

Lock maintenance

August 10

Lock E-7

Lock rehabilitation

July 20

Lock E-9

Movable dam maintenance

July 4                               Note 1

Waterford Flight

Lock maintenance

July 4

Lock C-1&2

Maintenance & buoy install

July 4

 

Note 1 – Locks E-8 and E-9 open after Lock E-7

*Start of work assumed to be June 1st to ensure all COVID-19 safety protocols are in place at the work sites.

For updates and information, please visit Canals.NY.gov or follow us on Facebook or Twitter