Skip to Main Content
Skip to Navigation
Skip to Main Content
Skip to Navigation
New York State Canal Corporation

Notice to Mariners

Erie Canal – Crescent & Vischer Ferry

Deceember 4, 2018

 

The Blenheim-Gilboa Project, working with the Canal Corporation, will remove flashboards at Crescent & Vischer Ferry Projects starting Monday, December 10, 2018 instead of Tuesday, November 27, 2018 as originally announced in a November 13th Notice to Mariners. The new schedule is as follows:

 

Saturday December 8, and Sunday, December 9

A gradual 2 to 2.5 foot water drawdown begins at Vischer Ferry as water levels between Mohawk River/Erie Canal Locks E7 & Lock E8 lower.  The water drawdown is completed by Monday morning. (Elevation 211.0’ BCD*)

 

Monday, December 10 

Morning: water levels at Vischer Ferry gradually rise approximately 2 to 2.5 feet to top of flashboards (normal water level during navigation season). (Elevation 213.1’ BCD*)

Morning: A 2-foot drawdown begins at Crescent as water levels between Mohawk River/Erie Canal Locks E6 & E7 lower.  Removal at Crescent is completed. (Elevation 183.5’ BCD*)

Afternoon: water levels at Crescent rise approximately 3 inches, to non-navigation season levels. (Elevation 183.8’ BCD*)

Overnight: Another 2 to 2.5 foot drawdown begins at Vischer Ferry as water levels between Mohawk River/Erie Canal Locks E7 & E8 lower a second time. Drawdown completed by Tuesday morning. (Elevation 210.5’ BCD*)

 

Tuesday, December 11

Morning: Canals scow travels from Lock 6 /Crescent Project to Lock 7 / Vischer Ferry Project.

Afternoon: With water levels at Vischer Ferry lowered 2 to 2.5 feet, removal of flashboards and fish deterrent systems begins. (Elevation 210.5’ BCD*)

Evening: water levels at Vischer Ferry rise approx. 7 inches. (Elevation 211.1’ BDC*)

 

Wednesday, December 12

Morning: water levels at Vischer Ferry drop approx. 7 inches. (Elevation 210.5’ BCD*) 

Removal of flashboards is complete.

Afternoon: water levels at Vischer Ferry rise approx. 3 inches, to non-navigation season levels. (Elevation 210.8’ BCD*)

 

Thursday, December 13

Scheduled as a planned contingency day for completing unfinished work.

 

*BCD refers to Barge Canal Datum

 

Barring any further complications or inclement weather, the flashboard removal will be completed by Friday, December 1, 2017. Unforeseen precipitation and/or high water conditions may delay this schedule.

 

Features along the eastern portion of the Erie Canal are listed by mileage at http://www.canals.ny.gov/wwwapps/navinfo/navinfo.aspx?waterway=erieeastern

For updates and information, please visit Canals.NY.gov or follow us on Facebook or Twitter.