August 28, 2018

 

The Blenheim-Gilboa Project will be closing the adult fish passage and opening the juvenile fish passage at the Vischer Ferry Project (adjacent to Erie Canal Lock E7) during the week of September 2.

The schedule is as follows:

  • Monday, Sept. 3 Water level at Vischer Ferry starts approaching crest in the PM.

  • Tuesday, Sept. 4 Water level at Vischer Ferry 0.5’ below crest by AM. The juvenile passage will be opened on Dam F, with the water level starting to rise by 11:00 AM.  Water level at Vischer Ferry will return to normal level in approximately 24 to 48 hours, depending on the river flow.

Unforeseen precipitation and high water conditions may delay this schedule or decrease the time to refill. Should you have any questions, please contact (518) 287-6340.

 

Chart 14786 E-38 showing the affected area can be found at http://www.canals.ny.gov/navinfo/charts/14786e38.png

Features along the eastern portion of the Erie Canal are listed by mileage at http://www.canals.ny.gov/wwwapps/navinfo/navinfo.aspx?waterway=erieeastern

For updates and information, please visit Canals.NY.gov or follow us on Facebook or Twitter