Skip to Main Content
Skip to Navigation

Schedule

  • Survey work starts in Brockport heading west to Medina on Monday, March 22. Work should be completed by close of business on Friday, March 26
  • Erosion and sediment controls installation begins in Brockport on Wednesday, March 24 heading west to Medina. Anticipated completion of work is Friday, April 2.
  • Scarification of embankment slopes and wildflower seed installation at select sites begins the week of March 24 in Brockport, heading west to Medina.
  • Planting installation is scheduled to begin around the week of April 12, beginning in Brockport and heading west to Medina.

***All work should be completed by the end of May. Trail restoration, if needed, will take place immediately after the plantings have been fully installed. Please check this page for schedule updates.***