EEIP Projected Schedule

EEIP SEQR Milestones
Task Date
Issue SEQR Determination October 30, 2019
Draft Scoping Document June 3, 2020
Public Review and Comment Early June to Early July 2020
Final Scoping Document February 3, 2021
Draft GEIS and Guidebook June 23, 2021
Public Review and Comment August 5, 2021 to October 15, 2021
Hold Public Hearings July 14, 2021
Final GEIS November 2021
Publish Finding Statements December 2021

* This is an anticipated schedule that complies with DEC regulatory timeframe requirements, however it is subject to change during the environmental review process. The Canal Corporation will update it as the environmental review process progresses.